Futureform’s latest project is the Victoria Hall Student Accommodation development next to
Wembley National Football Stadium.
The project will be one of the tallest Modular Buildings ever
constructed with modules going to 17 story’s high on the West Wing of
the development over looking the Stadium next door.
Futureform are working with Main Contractor Mace on this fast-track
project which only started foundation work on site in July 2010. The
first modules went into production at our Wellingborough Assembly Plant
in August and arrived on site at the end of September.
The Futureform modules designed for this project are exceptionally
large, being around 16m’s long and 3.8m’s wide. Internally they
generally consist of two fully fitted out bedrooms with en-suite shower
room at each end with a twin corridor in the middle section. At the end
of each “Wing” of the building there is a fully fitted out Living Room
with superb kitchen facilities.
The project of over 350 student accommodation rooms will be completed in
August 2011.
|